Journal No. 05 · The Direction · 5 min read · AJ Lammers, P.E.

Phase Zero: deciding before designing

The most expensive line on any drawing is the one you have to erase. Phase Zero is how this project is trying to erase lines before anyone draws them.

Romich Foundation Makerspace logo over an aerial view of the project site in Creston, Ohio

What Phase Zero is

On a typical project, the owner hires an architect and design starts right away. Schematic design, then design development, then construction documents. Big questions get answered along the way, often after a lot of drawing has already been done.

Phase Zero is a short, paid step in front of all that. On this project it runs about 30 days with MKC Architects. The goal is simple: settle the direction before committing to full design. That means confirming the program, understanding the site, and comparing the big choices side by side.

Why this project needs it

A conventional building has a well-worn path. Everyone knows how a slab, a furnace, and a utility meter work. This building has almost none of those defaults. Nearly every major system is a decision:

  • Foundation: several systems that eliminate concrete, compared against a conventional baseline
  • Floor framing and envelope: how the building is built and insulated without concrete
  • Water: rainwater harvesting, greywater reuse, and a backup supply
  • Heating and cooling: geothermal options and the HVAC approach
  • Power: solar with batteries, a microgrid, and EV charging
  • Resilience: grounding, shielding, and protection measures Barry asked to explore
  • Certification: LEED, with Living Building Challenge and WELL as comparisons

For each one, MKC is laying out the options with the same questions: What code path does it need? How risky is the permit? What does it cost, and what does it do for carbon? Which consultant would design it?

Every choice gets written down

Those answers feed a design-decision matrix that we keep as the owner's representative. It records every option considered and why one was picked over another.

That record does two jobs. It keeps the team from reopening settled questions six months from now. And it becomes part of what the Foundation plans to share publicly, so the next owner who wants to try this doesn't start from zero.

A month of decisions up front costs far less than a redesign halfway through.

Built to be replicated, not just admired

Barry is clear that this building should be a model others can realistically follow, not a showcase for an unlimited budget. So Phase Zero is set up to price sustainable features one at a time. If a feature doesn't earn its cost, it can come out without redesigning the whole building.

Cost discussions are also anchored to Wayne County pricing, not big-city numbers. We'll prepare an independent order-of-magnitude estimate from MKC's information, so the owner has a second set of numbers before setting a budget.

What comes out the other end

At the end of Phase Zero, the Foundation will have:

  1. A summary report with findings, constraints, and a recommended direction
  2. A conceptual site plan and floor plan
  3. A side-by-side comparison of the alternatives above
  4. A code and permitting strategy for the unconventional systems
  5. A recommended roster of consultants and draft scopes for each
  6. A full-services proposal based on what Phase Zero settled

That last item matters more than it looks. A design fee priced after the direction is clear is a fee priced on real scope, not on guesses.

Next time: a drill rig, a hayfield, and a group of FFA students.

For owners · The takeaway

If your project is simple and familiar, you may not need a formal Phase Zero. But if you're asking a design team to do something new, a short paid step to settle direction is cheap insurance. A month of structured decisions up front costs far less than a redesign halfway through construction documents.